2026 NEC References: 230.1, 230.2, 230.4
Article 230 establishes requirements for service conductors and equipment, including their control, protection, and installation.
Certain service-related equipment is specifically required to be listed, while other service equipment must be listed or field evaluated.
The general rule is:
One building or structure → one service.
But Article 230 provides several exceptions that allow additional services.
Does a meter socket always have to be listed?
Answer: No.
A meter socket does not have to be listed when it is supplied by and exclusively controlled by the electric utility.
230.1 — Scope
230.2 — Number of Services
230.4 — Service-Entrance Conductors
Don't jump straight into conductor sizing.
First understand what Article 230 covers and whether you're dealing with one service or an exception allowing additional services.
→ Continue to Quick Hit #02