Slide 1 — Hook "The disconnecting means section is huge — splitting it into two episodes. Today: the basics of where it goes and what it has to do."
Slide 2 — 267.31(A) & (B) General & Location
A means must be provided to disconnect ALL ungrounded conductors that supply OR pass through the building/structure.
Location: inside or outside the building, or where the conductors pass through it — readily accessible, nearest the point of entrance. If not readily accessible, it must be operable by mechanical linkage from a readily accessible point (or remote electrical control for multibuilding industrial sites under single management).
Exceptions mirror the Services article: documented-switching-procedure sites, electrolytic cell buildings (685.1), lighting-standard poles/towers, and sign-support poles all get location flexibility.
Slide 3 — 267.31(C) Type
Must simultaneously disconnect all ungrounded conductors it controls, with a fault-closing rating ≥ available fault current at its terminals (fuse characteristics can contribute to that rating).
If it lacks visible break contacts, an isolating switch is required (more on that next episode).
Exception: fused cutouts can skip simultaneous disconnection IF there's a way to disconnect the load first — with a required "DISCONNECT LOAD BEFORE OPENING CUTOUTS" sign.
Exception: documented-switching-procedure sites can use single-pole units (one per phase) instead.
Slide 4 — Quiz + CTA Q: "A building/structure disconnecting means must be capable of disconnecting what?" A) Only the grounded conductor B) All ungrounded conductors that supply or pass through the building C) Only conductors originating on-site D) Nothing specific — any disconnect qualifies
✅ Answer: B — 267.31(A): all ungrounded conductors supplying OR passing through the building.
CTA: Follow for more daily quick-hit study notes 📚⚡